DET NORSKE VERITAS
TYPE APPROVAL CERTIFICATE
This Certificate consists of 4 pages
This is to certify that the
with type designation(s)
Soluforce System 4" and 5" with in-line couplings and end fittings
Manufactured by
is found to comply with
DNV-OS-C501 "Composite components"
Ch 3 Design basis
Ch. 8 Safety factor
Ch 10 C Verification, short-and long term
Ch. 10 D Components testing
Application
Reinforced plastic pipes for transportation of water for industrial purposes.
Place and date |
This Certificate is valid until | |||||
for Det Norske Veritas AS |
||||||
Local Office |
||||||
Head of Section |
Surveyor | |||||
The pipe and couplings of polyethylene (PE) liner reinforced by aramid cords embedded in PE and covered by a PE cover, are approved for transportation of water for industrial purposes.
The design of the pipe body and couplings fulfils the requirements for low safety class applications with a design life of 20 years and water as a fluid, provided the stated limitations of use are accounted for.
Application/Limitation
Pipelife Trade name |
M480 |
M570 | |
Design Pressure, water |
MPa |
9.0 |
7.5 |
Design Temperature, max |
oC |
65 |
65 |
Design Temperature, min |
oC |
-10 |
-10 |
Internal Diameter |
mm |
98.5 |
125 |
External Diameter |
mm |
125 |
150 |
Design life |
years |
20 |
20 |
Max allowable tension |
kN |
10 |
10 |
· The pipe body is qualified only for water service.
· The application is for low safety class, i.e., small possibility for personal injuries and pollution, small economic consequences, negligible risk to life.
· The outer cover shall be inspected during operation for possible damage from the outer environment.
· If the pipe is buried the relevant standards for un-reinforced PE pipe shall be used to prevent buckling.
· Cars should not drive over the RTP pipe to prevent point loads from sharp stones.
· Lightning protection should be applied if relevant for the application.
· The RTP is only qualified for PE grade PE 100 and aramid tape made of grade PE 80 with fibres 3360 dtex x 5 Z45.
· The RTP has not been qualified for fatigue load conditions (cyclic pressure).
· The pipes are not fire resistant. Fire protection has to be obtained on the system level, if necessary.
Type Approval documentation
Drawing No. |
Rev. |
|
36-049-4 |
2 |
Samenstelling Electrolaseindkoppeling LLRTP 5" mel flens 6" 600 pond |
36-015-4 |
6 |
Samenstelling Electrolaseindkoppeling LLRTP 4" Flensaansluiting 600 Pand 6" - Gedeelde uitvoering |
36-007-1 |
6 |
Epoxy buitenmot voor Electrolasoppeling LLRTP 4" |
36-011-1 |
5 |
Epoxy buitenmot electroseindoppeling LLRTP 4" |
36-013-2 |
6 |
Samenstelling Kunststofdeel Electrolaseindkoppeling LLRTP 4" |
36-076-1 |
4 |
Epoxy buitenmot electroseindoppeling LLRTP 5" |
36-030-1 |
4 |
Epoxy buitenmot electroseindoppeling LLRTP 5 |
36-044-2 |
3 |
Samenstelling kunstofdeel electrolaseindkoppeling LLRTP 5" |
In field joining procedures:
- Hydrotesting of Soluforce pipe system Version 1.1.2003.
- Connecting Soluforce pipes Version 1.1.2003.
- Inst. Soluforce end-fitting steel parts Version 1.1.2003.
Tests carried out
Design requirements, prototype testing and design evaluation was documented in the following reports.
- DNV Tech. Report No. 2001-1078, rev. 3 "Reinforced thermoplastic pipes - design premises"
- DNV Tech. Report No. 2001-0870, rev. 01 "Design verification report reinforced thermoplastic pipe (RTP) pipe body for water service".
- DNV Tech. Report No. 2001-0872, rev. 02 "Design verification report reinforced thermoplastic pipe (RTP) 4" coupler for water service"
- DNV Tech. Report No. 2001-0871, rev. 02 "Design verification report reinforced thermoplastic pipe (RTP) 6" coupler for water service"
- DNV Tech. Report No. 2001-1212, rev. 03 "Long time regression curve for reinforced thermoplastic pipe (RTP)"
- DNV Tech. Report No. 2001-3135, rev. 01 "Reinforced thermoplastic pipes -4" pipe body process monitoring specification"
Fabrication
The pipes and couplings shall be produced under the quality system and with the fabrication parameters and quality control tests as described in DNV technical report No.: 2002-3135, rev. 1 "Reinforced thermoplastic pipes 4" pipe body process monitoring specifications.
Fabrication survey carried out 2004-05-25, (ref. No. 7240000-J-2996).
Marking of product
The product shall be marked with design limitations and product designation and manufacturers name and address:
- Diameter and Charge No.
- Production date
- M 480 or 570
- Max. Temp.
- Traceability for every produced meter of pipe
- Manufacturer name and country
Certificate retention survey
For retention of the Type Approval, the DNV-surveyor shall perform a survey every second year and before the expiry date of this certificate - to verify that the conditions for the type approval are complied with.
END OF CERTIFICATE
Notice: This Certificate is subject to terms and conditions overleaf. Any significant change in design or construction may render this Certificate invalid.
If any person suffers loss or damage which is proved to have been caused by any negligent act or omission of Det Norske Veritas, then Det Norske Veritas shall pay compensation to such person for his proved direct loss or damage. However, the compensation shall not exceed an amount equal to ten times the fee charged for the service in question, provided that the maximum compensation shall never exceed USD 2 million.In this provision "Det Norske Veritas" shall mean the Foundation Det Norske Veritas as well as all its subsidiaries, directors, officers, employees, agents and any other acting on behalf of Det Norske Veritas.
DET NORSKE VERITAS AS · VERITASVEIEN 1, 1322 HØVIK, NORWAY · TEL: (+47) 67 57 99 00 · FAX: (+47) 67 57 99 11