The electronic pdf versions of the documents found through http://www.dnv.com/ are the officially binding versions. Copyright Det Norske Veritas.

[Book] [Expand] [Collapse] [Search Forms] [Previous Section with Hits] [Next Section with Hits] [Clear Search] [Help]

Expand Search


F: Escape, Evacuation and Communications [Table of Contents] Sec.9: Special Provisions for LNG Import and  Export Terminals
(and LNG Production Units)

DNV-OS-A101 Safety Principles and Arrangements

[-] Sec.8: Special Provisions for Drilling Units
[-] F: Escape, Evacuation and Communications
[-] F100: General

Sec.8
F 100   General

Sec.8 F
101
   At least one escape route from the drilling derrick and from driller's cabin should lead directly to a safe place without requiring personnel entry to the central drill floor area.
F: Escape, Evacuation and Communications [Table of Contents] Sec.9: Special Provisions for LNG Import and  Export Terminals
(and LNG Production Units)