DNV-OSS-301 Certification and Verification of Pipelines

[-] Sec.3: Service Overview
[-] D: Certification
[-] D400: Verification during construction

Sec.3
D 400   Verification during construction

Sec.3 D
401
   Verification during construction is carried out by means of full time attendance, audits, inspection or spot checks of the work, as appropriate, in sufficient detail to ensure that the specified requirements of the pipeline system will be achieved.

Sec.3 D
402
   Verification of these activities relates not only to the contractor's work but also to the monitoring of this work carried out by others.

Sec.3 D
403
   During construction verification shall consist of one, or more, of:
reviewing the construction process,
reviewing construction procedures
reviewing qualification process
surveillance during construction activities
reviewing final documentation.


Sec.3 D
404
   The documents that shall be produced in the project are given in DNV-OS-F101 Sec.3 F300, F400, F500 and F600.

Sec.3 D
405
   Definition of scope of work for certification of construction shall follow Table 3-3 and Table 3-4 for manufacturing and fabrication, Table 3-5 for installation and Table 3-6 for final testing and completion.

Sec.3 D
Table 3-3 Scope of work for certification of manufacturing and fabrication of linepipe and other PRESSURE CONTAINING components 
Verification activity Level 
L M H 
Review of the manufacturing & fabrication process by    
review of manufacturing and fabrication management systems
 
audit of the quality management system
 
 
Review of manufacturing & fabrication procedures by    
review manufacturing, fabrication and inspection procedures for confirmation of compliance with the manufacturing specification
 
review method statements
 
 x 
Review of qualification process by    
review the Manufacturing Procedure Specification, (MPS), Manufacturing Procedure Qualification Test (MPQT), if applicable
 
full time attendance during MPQT, if applicable, or first day production
 
 
Surveillance during manufacturing and fabrication activities by    
visit-based attendance during testing, to ensure, based on spot checks, that the delivered products have been produced in accordance with the manufacturing specification
 
visit-based or full-time attendance during manufacturing and fabrication to ensure, based on spot checks, that the delivered products have been produced in accordance with the manufacturing specification
 
 
full-time attendance during manufacturing and fabrication to ensure, based on spot checks, that the delivered products have been produced in accordance with the manufacturing specification
 
  
FOR LINEPIPE PRODUCTION ONLY: overall independent verification of production must be sufficient for DNV to operate its independent quality system (QVS) to get an independent verification of the delivered pipes
 
  
Review of final documentation 

Sec.3 D
Table 3-4 Scope of work for certification of manufacturing and fabrication of coatings, anodes and other NON-PRESSURE CONTIANING components 
Verification activity Level 
L M H 
Review of the manufacturing & fabrication process by    
review of manufacturing and fabrication management systems
 
audit of the quality management system
 
  
Review of manufacturing & fabrication procedures by    
review manufacturing, fabrication and inspection procedures for confirmation of compliance with the manufacturing specification
 
 
Review of qualification process by    
review the Manufacturing Procedure Specification, (MPS), Manufacturing Procedure Qualification Test (MPQT), if applicable
 
full time attendance during MPQT, if applicable, or first day production
 
  
Surveillance during manufacturing and fabrication activities by    
visit-based attendance during testing, to ensure, based on spot checks, that the delivered products have been produced in accordance with the manufacturing specification
 
 
visit-based attendance during manufacturing and fabrication to ensure, based on spot checks, that the delivered products have been produced in accordance with the manufacturing specification
 
  
Review of final documentation 

Sec.3 D
Table 3-5 Scope of work for certification of installation 
Verification activity Level 
L M H 
Review of the installation process by    
review of installation management systems
 
audit of the quality management system
 
 
Review of installation procedures by    
spot check of Installation Manual, (IM)
 
for critical operations (identified from the FMEA and HAZOP studies) review the IM
 
 x 
Review of qualification process by    
for critical operations, review the qualification of the IM
 
full time attendance during qualification tests, if applicable, or production start-up
 
 
Surveillance during installation activities by    
visit-based attendance during start up of each offshore operation (i.e. pipelaying, riser installation, intervention works, etc.
 
full time attendance during tension trials and associated lay tests: visit- based attendance during laying
 
 
full time attendance at each offshore operation (i.e. pipelaying, riser installation, intervention works
 
  
Review of final documentation 

Sec.3 D
Table 3-6 Scope of work for certification of final testing for operation, including as-built survey and project completion 
Verification activity Level 
L M H 
Review of the process by    
review of management systems
 
audit of the quality management system
 
  
Review of procedures by    
review of the procedures for system pressure test to ensure that the test procedure will test the pipeline system in accordance with the design requirements
 
Surveillance during testing and completion activities by    
full time attendance during pressure testing (minimum 24 hrs)
 
full time attendance during testing and audit based attendance during cleaning, gauging, de-watering and drying. Visit-based attendance during as-built surveying
 
  
Review of final documentation by    
spot check of as-built documentation
 
review of as-built documentation
 
   