The electronic pdf versions of the documents found through http://www.dnv.com/ are the officially binding versions. Copyright Det Norske Veritas.
|
DNV-OSS-301 Certification and Verification of Pipelines
|
SECTION 2
Principles of Risk-Differentiated
Certification
and VerificationSec.2
A. General
Sec.2
A 100 Objectives
Sec.2 A
101 The objectives of this section are to provide:
| — | introduction to the principles
of certification and verification of pipeline systems |
| — | introduction to the principles of risk differentiated
levels of verification activity |
| — | guidance on the selection of levels of certification
and verification. |
Sec.2
B. Verification Principles
Sec.2
B 100 Purpose of verification
Sec.2 B
101 Verification constitutes a systematic and independent examination
of the various phases in the life of a pipeline system to determine
whether it has (or continues to have) sufficient integrity for its
purpose.
Sec.2 B
102 Verification activities are expected to identify errors or failures
in the work associated with the pipeline system and to contribute
to reducing the risks to the operation of the pipeline system and
to the health and safety of personnel associated with it or in its
vicinity.
Sec.2 B
103 Verification is primarily focused on integrity and (human)
safety, but business risk (cost and schedule) may be addressed also.Sec.2
B 200 Verification as a complementary
activity
Sec.2 B
201 Verification shall be complementary to routine design, construction
and operations activities and not a substitute
for them. Therefore, although verification will take
into account the work, and the assurance of that work, carried out
by the o owner and its contractors, it is inevitable that certification
will duplicate some work that has been carried out previously by other
parties involved in the pipeline system.
Sec.2 B
202 Verification shall be developed and implemented in such a
way as to minimise additional work, and cost, but to maximise its
effectiveness. This development of verification shall depend on
the findings from the examination of quality management systems,
the examination of documents and the examination of production activities.Sec.2
B 300 Verification management
Sec.2 B
301 The certification philosophy and verification methods used
will be described to ensure satisfactory completion of certification
and verification.
Sec.2 B
302 The philosophy and these methods will ensure that certification
and verification:| — | have a consistent and constructive
approach to the satisfactory completion and operation of the pipeline
system |
| — | are available world-wide wherever the owner or his contractors
operate |
| — | use up-to-date methods, tools and procedures |
| — | use qualified and experienced personnel. |
Sec.2 B
303 All certification and verification activities will be carried
out by competent personnel. Competence includes having the necessary
theoretical and practical knowledge and experience of the activity
being examined. An adequate verification of some activities may
require access to specialised technical knowledge.
Sec.2 B
304 As well as demonstrating competence of individuals, the verification
organisation also will be able to show competence and experience
in pipeline verification and certification work.Sec.2
B 400 Risk-Differentiated Levels of
Certification and Verification
Sec.2 B
401 To achieve a DNV Certificate of Conformity for a pipeline
system a verification of the activities described by the scope of
work defined within this OSS shall first take place.
Sec.2 B
402 The level of verification activity is differentiated according
to the risk to the pipeline. If the risk to the pipeline is higher,
the level of verification involvement is higher. Conversely, if
the risk to the pipeline is lower, the level of verification activities
can be reduced, without any reduction in their effectiveness.
Sec.2 B
403 It is emphasised that the activity level describes the depth
of the verification involvement and not different certificate levels.
It follows, therefore, that an increase in the level of involvement
above that considered necessary, based on an evaluation of the risks,
involves minimal extra risk reduction for increased cost. This practice
is unlikely to be cost-effective.
Sec.2 B
404 Certification of pipeline systems is categorised into low, medium and high. A summary of the levels of
involvement is given in Table 2-1.| Medium | | is the customary level of certification activity and is applied
to the majority of pipelines. |
| High | | is the level of certification applied where the risks to the
pipeline are higher because, for example, it has highly corrosive
contents, it is in adverse environmental conditions, it is technically
innovative or the contractors are not well experienced in the design and
construction of similar pipelines. |
| Low | | is the level of certification applied where the risks to the
pipeline are lower because, for example, it has benign contents,
it is located in congenial environmental conditions, or the contractors
are well experienced in the design and construction of similar pipelines. |
Sec.2 B
405 It is the prerogative of the owner of the pipeline system to
choose the level of certification. The selection should consider
the factors given in Sec.2 B.
The selection of the most suitable certification level may be guided
by using the questions proposed in Appendix
A.
Sec.2 B
406 As DNV is issuing the pipeline certificate, DNV will use the
same type of questions to evaluate the suitability of the selected
level.
Sec.2 B
407 Different levels of certification can be chosen for different
phases of the pipeline system, or even within the same phase if
necessary. For example, pipeline design may be innovative and considered
high risk whereas the installation method is well known and considered
low risk. The converse might be true also.Additionally, linepipe production from a well known mill may be
considered low risk, whereas, production from an unknown mill may
be considered high risk.
Sec.2 B
408 The level of certification can be reduced or increased during
a phase if the originally chosen level is considered too rigorous
or too lenient, as new information on the risks to the pipeline
system becomes available.
Sec.2 B
409 Certification should be planned in close co-operation with
the owner and each of its contractors, to provide a scope of work
that is tailor-made to the schedule of each production process/activity,
i.e. to make the verification activities, surveillance and hold
points, an integrated activity and not a delaying activity.
Guidance note:
Many Contractors have adequate quality control systems and quality
control departments, with competent personnel to perform, for example,
inspection at mills and coating plants and specialist material engineers
competent to review and verify the performance of mills.
In that case, all certification work need not be done by DNV
personnel. Where applicable, the various inspections may be carried out
by competent persons other than DNV personnel.
In that situation DNV's certification activities
can be confined to:| - | reviewing the competence of
the contractor's personnel| - | auditing their working methods and their performance
of that work| - | reviewing the documents produced by them. | | |
---e-n-d---o-f---G-u-i-d-a-n-c-e---n-o-t-e---
Sec.2 B
410 Certification will direct greatest effort at those elements of
the pipeline system whose failure or reduced performance will have
the most significant impact on safety as well as project risk.
Sec.2 B
411 The degree of confidence placed in a certificate by its users
depends on their degree of confidence in the certification carried
out. Therefore, the level of certification will be stated on the
pipeline certificate.
Sec.2 B
412 If more than one certification level has been used for a phase,
then the lowest level will be reported on the statement(s) and the
pipeline certificate, and the additional verification activities
will be identified and described in the verification report(s).Sec.2
C. Selection of Level of Certification
Sec.2
C 100 Selection factors
Sec.2 C
101 The selection of the level of certification shall depend on the
criticality of each of the elements that have an impact on the management
of hazards and associated risk levels of the pipeline system. This
is illustrated by Fig. 1.The
contribution of each element shall be judged qualitatively and/or
quantitatively and shall use, where possible, quantified risk assessment
data to provide a justifiable basis for any decisions made.Sec.2 C
| Table 2-1 Levels
of Certification - Summary of Involvement |
| Level | Description of involvement | Guidance for application
on the level of involvement |
| Low | | — | Review
of general principles and production systems during design and construction. | | — | Review of principal design documents, construction procedures
and qualification (e.g. MPQT) reports. | | — | Visit-based attendance during system testing and start-up
activities. | | — | Less comprehensive involvement than level Medium. | | | — | Proven
pipeline designs with benign contents and/or installed
in benign environmental conditions. | | — | Straightforward pipelines designed and constructed by
experienced contractors. | | — | Low consequences of failure from a safety, environmental
or commercial point of view. | | — | Relaxed to normal completion schedule. | |
| Medium | | — | Review
of general principles and production systems during design and construction. | | — | Detailed review of principal and other selected design documents
with support of simplified independent analyses. | | — | Full time attendance during (procedure) qualification (e.g.
MPQT) and review of the resulting reports. | | — | Visit-based or intermittent presence at site. | | | — | Pipelines
in moderate environmental conditions. | | — | Projects with a moderate degree of novelty. | | — | Medium consequences of failure a safety, environmental
or commercial point of view. | | — | Ordinary completion schedule. | |
| High | | — | Review
of general principles and production systems during design and construction. | | — | Detailed review of most design documents with support
of simplified and advanced independent analyses. | | — | Full time attendance during (procedure) qualification (e.g.
MPQT) and review of the resulting reports. | | — | Full time presence at site for most activities. | | — | More comprehensive involvement than level Medium. | | | — | Innovative
pipeline designs in extreme environmental conditions. | | — | Projects with a high degree of novelty or large leaps
in technology. | | — | Inexperienced contractors or exceptionally tight completion schedule. | | — | Very high consequences of failure a safety, environmental
or commercial point of view. | |
Sec.2 C
102 Selection factors are the:| — | overall safety objectives for
the pipeline system |
| — | assessment of the risks associated with the pipeline
and the measures taken to reduce these risks |
| — | degree of technical innovation in the pipeline system |
| — | experience of the contractors in carrying out similar
work |
| — | quality management systems of the owner and its contractors. |
Guidance note:
Each of these factors is addressed also in DNV-OS-F101 Section 2.B.---e-n-d---o-f---G-u-i-d-a-n-c-e---n-o-t-e---
Fig. 1 Selection of the required level of certification
Sec.2
C 200 Overall safety objective
Sec.2 C
201 An overall safety objective covering all phases of the pipeline
system from design to operation should be defined by the owner.
The safety objective should address the main safety goals as well
as establishing acceptance criteria for the level of risk acceptable
to the owner. Depending on the pipeline and its location the risk
could be measured in terms of human injuries as well as environmental,
political and economic consequences. Sec.2
C 300 Assessment of risk
Sec.2 C
301 A systematic review should be carried out to identify and
evaluate the probabilities and consequences of failures in the pipeline
system. The extent of the review shall reflect the criticality of
the pipeline system, the planned operation and previous experience
with similar pipeline systems. This review shall identify the risk
to the operation of the pipeline system and to the health and safety
of personnel associated with it or in its vicinity.
Sec.2 C
302 Once the risks have been identified their extent can be reduced
to a level as low as reasonably practicable by means of one or both
of:| — | reduction in the probability
of failure |
| — | mitigation of the consequences of failure. |
Guidance note:
Reasonable practicability
The term "as low as reasonably practicable (ALARP)" has
come into use through the United Kingdom's "The
Health and Safety at Work etc. Act 1974". Reasonable Practicability
is not defined in the Act but has acquired meaning by interpretations
in the courts.
It has been interpreted to mean that the degree of risk from
any particular activity can be balanced against the cost, time and
trouble of the measures to be taken to reduce the risk.
It follows, therefore, that the greater the risk the more
reasonable it would be to incur substantial cost, time and effort
in reducing that risk. Similarly, if the risk was very small it
would not be reasonable to expect great expense or effort to be
incurred in reducing it.---e-n-d---o-f---G-u-i-d-a-n-c-e---n-o-t-e---
Sec.2 C
303 The result of the systematic review of these risks is measured
against the safety objectives and used in the selection of the appropriate
certification activity level.Sec.2
C 400 Technical innovation and contractor
experience
Sec.2 C
401 The degree of technical innovation in the pipeline system
shall be considered. Risks to the pipeline are likely to be greater
for a pipeline with a high degree of technical innovation than with
a pipeline designed, manufactured and installed to well-known criteria
in well-known waters.
Sec.2 C
402 Similarly, the degree of risk to the pipeline system should
be considered where contractors are inexperienced or the work schedule
is tight.
Sec.2 C
403 Factors to be considered in the selection of the appropriate
certification level include:| — | degree of difficulty in achieving
technical requirements |
| — | knowledge of similar pipelines |
| — | knowledge of contractors' general pipeline
experience |
| — | knowledge of contractors' experience in similar
work. |
Sec.2
C 500 Quality management systems
Sec.2 C
501 Adequate quality management systems shall be implemented to
ensure that gross errors in the work for pipeline system design,
construction and operations are limited.
Sec.2 C
502 Factors to be considered when evaluating the adequacy of the
quality management system include:| — | whether or not an ISO 9000 or
equivalent certified system is in place |
| — | results from external audits |
| — | results from internal audits |
| — | experience with contractors' previous work |
| — | project work-force familiarity with the quality management
system, e.g. has there been a rapid expansion of the work force
or are all parties of a joint venture familiar with the same system. |
Guidance note:
Most organisations have quality management systems certified by
an accredited third party certification body. However, when business
increases, they expand their staff quickly by taking on contract
personnel often for a fixed period or for the duration of a particular
contract.
This influx of new personnel can lead to problems of control
of both the whole organisation and of particular projects being
undertaking. Quality problems may then occur, as these new personnel
have no detailed knowledge of the organisation's business methods,
its ethos or its working procedures. ---e-n-d---o-f---G-u-i-d-a-n-c-e---n-o-t-e---
Sec.2
D. Information Flow
Sec.2
D 100 Communication lines
Sec.2 D
101 Communication lines are illustrated in Figure
2. Which lines that are open for communication depends on
the particular contractual agreements.
Sec.2 D
102 For instances where DNV (3rd party) does not have a contract
with the owner (1st party), DNV recommends strongly that the owner,
through his contract with the 2nd party, secures a direct communication
line from DNV to owner and vice versa.Guidance note:
The recommendation springs from DNV's experience
with projects where communications difficulties between the parties have
jeopardised the issue of the pipeline certificate.---e-n-d---o-f---G-u-i-d-a-n-c-e---n-o-t-e---
Fig. 2 Communication Lines
Sec.2
D 200 Obligations
Sec.2 D
201 In order to achieve the purpose and benefits of certification
the involved parties shall be mutually obliged to share and act
upon all relevant information pertaining to the certification scope.
Sec.2 D
202 The owner shall be obliged to:| — | inform DNV about the basis for
selecting the level of certification and the investigations and
assumptions made in this context |
| — | give DNV full access to all information concerning the certification
scope for the pipeline system and ensure that clauses to this effect
are included in contracts for parties acting on behalf of the owner
and parties providing products, processes and services covered by
the certification scope |
| — | ensure that DNV is involved in the handling of deviations from
specified requirements within the certification scope |
| — | act upon information provided by DNV with respect to events
or circumstances that may jeopardise the pipeline system and/or
the purpose and benefit of certification |
| — | ensure that the safety objective established for the
pipeline project is known and pursued by parties acting on behalf of
the owner and parties providing products, processes and services
covered by the certification scope. |
Sec.2 D
203 2nd parties shall
be obliged to:| — | perform their assigned tasks
in accordance with the safety objective established for the pipeline
project. |
| — | provide the owner and DNV with all relevant information pertaining
to the certification scope. |
Sec.2 D
204 DNV will be obliged to:| — | inform the owner if, in the
opinion of DNV, the basis for selecting the level of certification
or the assumptions made in this respect are found to be in error
or assessed incorrectly |
| — | inform the owner of events or circumstances that, in
the opinion of DNV, may jeopardise the pipeline system and/or
the purpose and benefit of certification |
| — | effectively perform all certification work and adjust
the level of involvement according to the actual performance of
parties providing products, processes and services covered by the
certification scope. |
Sec.2
D 300 Notification of certification
level
Sec.2 D
301 An assessment of the required level of certification for a project
should be made by the owner before preparing tender documents for
design and construction activities. The owner can then specify this
level in Invitation to Tender. This will give contractors clear
guidance and reference when estimating the extent and cost of efforts
associated with certification activities.
Sec.2 D
302 The required level of certification can be assessed by the owner
using this OSS. However, if the owner requires the contractor to
carry out this assessment as part of his response to an Invitation
to Tender (ITT) the owner should provide the necessary information
to enable the contractor to carry out this work. This information
should include overall safety objectives for the pipeline system
as well as particulars, such as temperatures, pressures, contents
and environmental criteria, commonly contained in a design brief.Guidance note:
Frequently, ITTs contain one line stating "....
the contractor shall arrange 3rd party verification." The
use of the information contained in the above paragraphs should
assist the owner to specify the required level of certification
more precisely.
On other occasions, certification is arranged by the owner
but, in this case, it is important that contractors are informed
of the level of certification planned.
The contractor's technical activities should not
be affected greatly by the contractual arrangements, aside from
whether or not the owner or the contractor assesses the required
level of certification.
There will be a small administration workload regarding document
control or meetings and discussions with the verifier but the contractor
can plan what documents are need to be seen by the verifier using
the information in this OSS. However, it is emphasised that the
verifier should not need to review any document that the contractor
would not produce normally when following the requirements of DNV-OS-F101.---e-n-d---o-f---G-u-i-d-a-n-c-e---n-o-t-e---